Are Welded Mesh Panels Better Than Chain Link Panels?

Keep temporary fencing within a site boundary by marking a fence line far enough inside the confirmed boundary to contain the entire system: panels, feet, braces, ballast, anchors, and the full gate swing. Measure the outward projection of the actual components before setting that line. Install the specified supports, then check for movement after weather, impacts, and gate use.

The panel face is not the outer limit of the installation. A straight run can still encroach if a foot projects onto the pavement or an open gate crosses into neighbouring land. HSE guidance for construction sites in Great Britain calls for the perimeter to be planned, provided, and maintained as part of protecting the public [1].

Confirm the Boundary and the Area You May Use

Start with the property documents, lease limits, site drawings, and reliable survey information. The area available to the contractor may be smaller than the whole property. Do not assume that a kerb, hedge, old fence, or painted mark identifies the line you are allowed to occupy.

A plan is not always precise enough for a tight fence placement. In England and Wales, GOV.UK explains that most title plans do not show exact boundaries [2]. If the position is unclear or disputed, have it resolved with the landowner and an appropriately qualified surveyor before setting out the fence.

Reference What it establishes
Confirmed boundary and permitted work area The limits within which the installation must fit
Inner fence line The panel or post reference line, set back enough to contain all associated components

Permission to work on a site is not permission to occupy the pavement or neighbouring land. In England and Wales, scaffolding or hoarding on a public highway requires a local-authority licence [3]. That source addresses scaffolding and hoarding; check the local authority’s requirements for the particular mesh-fence installation rather than assuming identical licensing rules.

Any proposed use of land outside the confirmed work area needs separate permission and any applicable public-land approvals. Such an arrangement is an approved off-site occupation, not a fence kept wholly within the original boundary.

Set the Fence Back for Its Full Footprint

When comparing temporary fencing and wire mesh systems, request the installed assembly drawing, not just the panel dimensions. Identify a clear reference, such as the panel face or post centreline, and measure outward from it to the furthest component.

  • Feet: check their complete width and the permitted orientation.
  • Braces and ballast: allow for corner, end, and gate supports, including anything extending beyond a straight run.
  • Connections and lean: account for the installed panel position, not just a line drawn beneath it.
  • Gates and anchors: include the moving gate leaf, hinge offsets, support hardware, and the full anchor arrangement.

For a straight run, set the reference line inward by at least the greatest outward projection, plus an allowance for setting-out and installation tolerances. Select that allowance with the installer or designer for the actual system and site; a generic distance cannot establish a suitable setback. At corners and gates, draw and check the complete outline instead of relying on one offset measurement.

Mark the agreed inner line with string, chalk, or ground paint. Check it against the confirmed boundary at ends, corners, and changes in direction. If the required bracing does not fit, move the line inward or select another suitable system. Do not remove supports, reduce ballast, or rotate feet against the manufacturer’s instructions just to gain space.

Match Panel Quantities to the Available Run

Measure each straight run between the planned corners and gate bays. Haisen’s Canadian-style temporary fence panels are listed at a nominal 6 ft height with 8 ft, 9.5 ft, and 10 ft lengths. Listed wire options are 3.0, 3.5, or 3.8 mm, with 25 × 25 or 30 × 30 mm square-tube outer frames. These are supplier options, not proof that a particular assembly meets site requirements.

Nominal panel size Approximate metric size Calculated panel face area
6 × 8 ft 1.83 × 2.44 m 4.46 sq m
6 × 9.5 ft 1.83 × 2.90 m 5.30 sq m
6 × 10 ft 1.83 × 3.05 m 5.57 sq m

These conversions use 1 ft = 0.3048 m and are rounded from the nominal dimensions. Panel face area is not the ground footprint or a wind-load rating. Confirm actual installed coverage, joint allowances, and support projections from the supplier’s drawing before ordering.

What Our Layout Calculation Shows

For this guide, we recalculated a 60 ft straight run using the listed nominal panel lengths. Six 10 ft panels total 60 ft, but eight 8 ft panels total 64 ft. Rounding the quantity up therefore does not necessarily produce a fence that fits.

Available run Using 10 ft panels Using 8 ft panels
60 ft, approximately 18.29 m 60 ÷ 10 = 6 panels; 60 ft nominal coverage 60 ÷ 8 = 7.5; rounding to 8 panels gives 64 ft, or 4 ft excess

This is a desk-based calculation, not an installation test. It assumes one straight run, nominal widths, no joint allowance, and no gate. Even the six-panel result needs checking against installed dimensions. Where a run does not fit, revise the panel combination, use a manufacturer-approved infill, or redesign the layout; do not push the last panel beyond the boundary.

Keep Height Compliance Separate from Boundary Fit

WorkSafe Victoria’s construction-site guidance says security fencing should be at least 1.8 m high; demolition may require a higher fence depending on the risk [4]. In Great Britain, HSE says that fencing in populated areas will typically be a 2 m-high small-mesh fence or hoarding [1].

A nominal 6 ft panel is about 1.83 m high: above 1.8 m, but about 0.17 m below 2 m. These are different jurisdictions, not interchangeable approvals. Check finished height, mesh, climb resistance, ground clearance, and installation against the requirements applying to the site.

Reserve Space for Gates and Corners

Place gate bays before calculating the remaining panel quantities. Include posts, supports, hinges, latches, and the entire operating envelope of the chain-link gate assembly. Confirm that the gate and its supports are suitable for the selected fence system.

For example, a 60 ft run with a 12 ft overall gate bay leaves 48 ft for panels: 60 − 12 = 48. The 12 ft figure is an illustrative reserved bay, not a Haisen gate specification or a statement of clear opening width.

Check the Gate’s Swept Outline, Not Just Its Area

Draw the leaf in both its closed and fully open positions and trace the path between them. A 90-degree swing describes a quarter-circle sector: area = π × leaf length² ÷ 4, ignoring leaf thickness and hardware offsets.

Illustrative leaf length Calculated area swept through 90 degrees
6 ft About 28.3 sq ft, or 2.6 sq m
12 ft About 113 sq ft, or 10.5 sq m

Area alone does not show whether a gate fits. The hinge position, sweep radius, opening direction, and nearby obstructions determine whether any part crosses the boundary. These figures do not establish vehicle turning clearance. If a single leaf cannot operate inside the site, consider a recessed gate bay, two shorter leaves, or a compatible sliding arrangement with sufficient travel space.

At corners, check brace projections on both adjoining runs. On slopes or soft ground, review footing support and panel lean. Keep gates, braces, and anchors within the work area rather than treating space beyond the line as spare installation room.

Install the Supports Without Creating a New Hazard

Follow the manufacturer’s installation sequence and support details. WorkSafe Victoria says proprietary systems should be installed to the manufacturer’s specifications, with securely connected gates and joints and stability under anticipated forces such as strong winds [4]. A fence that fits only after required supports are omitted is not a suitable layout.

Keep each installed section aligned with the marked inner line and supported as specified. Before handover, inspect from both sides where access is lawful and safe. Check the upper panel edge as well as ground-level feet: a leaning panel can project beyond the line even when its base remains inside.

Screening changes the support question. WorkSafe Victoria warns that signage and shade-cloth coverings may require additional support to resist wind loading [4]. Review the assembly before adding coverings, and check that any additional braces or ballast still fit. Do not assume that an unscreened layout has the same support requirements once covered.

Check Buried Services Before Driving or Drilling

Freestanding feet do not penetrate the ground, but an assembly may still need stakes, anchors, or driven steel posts. Check those components before choosing a system for a no-dig area.

HSE’s excavation guidance says to obtain and review information about buried services, treat plans as indicative rather than exact, and have underground cables located, identified, and clearly marked by a competent person using suitable locating devices before work begins [5]. That guidance addresses excavation; apply the same caution when planning driven fence fixings rather than assuming a short stake is harmless.

Confirm permitted fixing positions, depths, and any required permits or owner approvals. Drilling a slab also requires checking that the substrate and anchor design suit the fence. Owner permission does not establish structural suitability, and neither approval authorises occupation beyond the agreed work area.

Check for Movement and Record Corrections

Assign responsibility for checking the fence. HSE advises regularly checking and reviewing site security so fencing or hoarding remains maintained and in good order [6]. Set the inspection routine according to the site risk assessment and the system’s instructions, rather than treating one interval as universal.

  • Recheck after strong wind, heavy rain, impacts, or changes to screening and layout.
  • Look for displaced feet, leaning panels, loose connections, shifted braces, and settlement.
  • Check gate operation during use; investigate dragging leaves or rocking supports.
  • Compare the installation with the original reference marks, including the full open-gate position.
  • Record the date, location, issue, corrective action, and person responsible.

If a component has moved outside the line, have the site team make the affected area safe and arrange correction using the specified installation method. Do not simply remove the projecting support. Repeated movement needs a review of the ground, support arrangement, exposure, or layout by the supplier or a competent designer.

Keep materials away from the fence and public routes clear. HSE recommends storing materials within the site perimeter, preferably in secure compounds or away from perimeter fencing, and warns that obstructing pavements during deliveries can force pedestrians into the road [1]. Clear vegetation or obstructions outside the site only where you have lawful access and permission.

Get the Right Issue Resolved Before Handover

Use a surveyor for an uncertain boundary, the local authority for public-land occupation, a utility locator or utility owner for buried services, and the supplier or a competent engineer for support and wind suitability. Keep the agreed line, component layout, gate positions, and fixing permissions in the site record.

The final check is physical: every fixed component and the complete gate operating envelope must fit within the confirmed work area. A panel count or a tidy-looking fence face cannot establish that on its own.

Planning a fence close to the boundary? Send your run lengths, available setback, gate openings, and ground conditions.

Ask Haisen to confirm panel dimensions and the proposed component arrangement before ordering.

Request a Quote